1Opinion of the Court
BOREMAN, District Judge.
Plaintiff, United States of America, hereinafter variously referred to as *675“plaintiff”, “United States” or “Government”, brought this action against defendant to recover damages for alleged breach of contract. In the first count of the complaint, plaintiff charges: That it entered into a contract with defendant whereby defendant agreed to deliver certain materials by a certain date; that after an extension of time within which to make said deliveries, defendant still failed to do so; that plaintiff notified defendant of the default and terminated the contract pursuant…
2Cases cited8 opinions
- United States v. United States Fidelity & Guaranty Co.Supreme Court of the United States · 1940
- United States v. ShawSupreme Court of the United States · 1940
- Nassau Smelting & Refining Works, Ltd. v. United StatesSupreme Court of the United States · 1924
- United States v. SilvertonCourt of Appeals for the First Circuit · 1952
- United States v. Nipissing Mines Co.Court of Appeals for the Second Circuit · 1913
3 more not listed; retrieve them via the Exa API.
3Cited by3 opinions
- United States v. Ameco Electronic CorporationDistrict Court, E.D. New York · 1963
- United States v. Buffalo Coal Mining CompanyDistrict Court, D. Alaska · 1959
- United States v. RudisDistrict Court, N.D. Illinois · 1959