Triax Pacific, Inc. v. Togo D. West, Jr., Secretary of the Army
Court of Appeals for the Federal Circuit
1Opinion of the Court
BRYSON, Circuit Judge.
Triax Pacific, Inc., appeals a decision of the Armed Services Board of Contract Appeals denying its request for an equitable adjustment of a contract to renovate military housing. Because the contract contained ambiguities on its face sufficient to place a reasonable contractor on notice, we apply the “patent ambiguity” doctrine and uphold the decision of the Board of Contract Appeals.
I
In 1990, the Army issued a bid solicitation to renovate 21 military housing units at Fort Shatter, Hawaii. The solicitation called for the construction of new lanais (covered, screened…
2Cases cited10 opinions
- Fortec Constructors v. The United StatesCourt of Appeals for the Federal Circuit · 1985
- Beacon Construction Co. of Massachusetts v. United StatesUnited States Court of Claims · 1963
- Newsom v. United StatesUnited States Court of Claims · 1982
- Interstate General Government Contractors, Inc. v. Michael P.W. Stone, Secretary of the ArmyCourt of Appeals for the Federal Circuit · 1992
- Interwest Construction v. Jesse Brown, Secretary of Veterans AffairsCourt of Appeals for the Federal Circuit · 1994
5 more not listed; retrieve them via the Exa API.
3Cited by111 opinions
- Nvt Technologies, Inc. v. United StatesCourt of Appeals for the Federal Circuit · 2004
- Linc Government Services, LLC v. United StatesUnited States Court of Federal Claims · 2010
- Blackwater Lodge & Training Center, Inc. v. United StatesUnited States Court of Federal Claims · 2009
- Joseph Dureiko, as Trustee, and Southern Pine Isle Corporation v. United StatesCourt of Appeals for the Federal Circuit · 2000
- Metcalf Construction Co. v. United StatesUnited States Court of Federal Claims · 2002
106 more not listed; retrieve them via the Exa API.