In re Zaleta
United States Bankruptcy Court, S.D. Florida.
1Opinion of the Court
ORDER ON REMAND
THOMAS C. BRITTON, Bankruptcy Judge.
An Order Transferring Proceeding entered July 28,1981,13 B.R. 144, (C.P. No. 7) in this ancillary adversary proceeding was appealed to the District Court. On January 26, 1983, the matter was remanded by the District Court, Judge Eaton:
“. .. for a determination of the jurisdictional issue under the Bankruptcy Court’s view of the present state of the law bearing on this case and for the entry of any further order not inconsistent with this ruling.”
The Order of Remand reached this court on January 28, but was not brought to my attention by the…
2Cases cited7 opinions
- Northern Pipeline Construction Co. v. Marathon Pipe Line Co.Supreme Court of the United States · 1982
- Briney v. Burley (In Re Burley)United States Bankruptcy Court, C.D. California · 1981
- Ed Dills, D/B/A Mid-Georgia Supply v. The City of Marietta, Georgia, and Mayor and Council of the City of Marietta, GeorgiaCourt of Appeals for the Eleventh Circuit · 1982
- Briney v. Burley (In Re Burley)United States Bankruptcy Appellate Panel for the Ninth Circuit · 1982
- Meriwether Federal Savings & Loan Ass'n v. Whitehorn (In Re Whitehorn)United States Bankruptcy Court, N.D. Georgia · 1981
2 more not listed; retrieve them via the Exa API.
3Cited by1 opinion
- Churchill Cabinet Co. v. Continental Illinois National Bank & Trust Co. of Chicago (In Re Destron, Inc.)United States Bankruptcy Court, N.D. Illinois · 1984