Everett Plywood Corp. v. United States
United States Court of Claims
1Opinion of the CourtNichols, Judge
The issues presented in this breach of contract case are (1) whether, under the doctrines of frustration or sovereign acts, the government may cancel a timber contract because of anticipated environmental damage without being liable for breach damages, (2) if the government is liable what the appropriate measure of damages is, and (3) whether the Contract Disputes Act of 1978, 41 U.S.C. §§ 601-613 (Supp. II 1978) (Act), authorizes the award of interest. For the reasons discussed herein, we hold that the government is liable for damages resulting from a breach of the contract, and we set forth…
2Cases cited15 opinions
- United States v. Utah Construction & Mining Co.Supreme Court of the United States · 1966
- Lynch v. United StatesSupreme Court of the United States · 1934
- United States v. SpearinSupreme Court of the United States · 1918
- Perry v. United StatesSupreme Court of the United States · 1935
- G. L. Christian and Associates v. The United StatesUnited States Court of Claims · 1963
10 more not listed; retrieve them via the Exa API.
3Cited by36 opinions
- Winstar Corp. v. United StatesCourt of Appeals for the Federal Circuit · 1995
- Seaboard Lumber Company and Capital Development Company v. United StatesCourt of Appeals for the Federal Circuit · 2002
- Brookfield Construction Co. v. United StatesUnited States Court of Claims · 1981
- Cienega Gardens v. United StatesUnited States Court of Federal Claims · 1995
- Winstar Corp. v. United StatesUnited States Court of Claims · 1992
31 more not listed; retrieve them via the Exa API.