Boyd v. Benkelman Public Housing Authority
Nebraska Supreme Court
1Opinion of the CourtNewton, J.
This is an action brought by a subcontractor to recover, for work and materials furnished on a construction prog*70ect, from the surety on the performance bond of the defaulting principal contractor and from the owner of the project. The district court found for the defendants and we affirm the judgment so entered.
The Benkelman Public Housing Authority entered into a contract with the Joe Dougherty Construction Company for the construction of a housing project. United Bonding Insurance Company became surety on Dougherty’s bond as required by section 52-118, R. R. S. 1943. Plaintiff subcontracted…
2Cases cited4 opinions
- Gatchell v. HendersonNebraska Supreme Court · 1952
- Reynolds v. Omaha General Iron WorksNebraska Supreme Court · 1920
- Rosebud Lumber & Coal Co. v. HolmsNebraska Supreme Court · 1952
- Westinghouse Electric Supply Co. v. BrookleyNebraska Supreme Court · 1964
3Cited by5 opinions
- Lindsay Manufacturing Co. v. Universal Surety Co.Nebraska Supreme Court · 1994
- Moglia v. McNeil Co., Inc.Nebraska Supreme Court · 2005
- Barnes v. HamptonNebraska Supreme Court · 1977
- John Day Co. v. Alvine & Associates, Inc.Nebraska Court of Appeals · 1993
- Boyd v. Benkelman Public Housing AuthorityNebraska Supreme Court · 1972