Bermont Operating Corp. v. City of New York
New York Court of Appeals
1Opinion of the Court
OPINION OF THE COURT
Memorandum.
The order of the Appellate Division should be affirmed, with costs.
The Appellate Division properly found that the parties had manifested their assent to a renewal lease with a term commencing on March 3, 1979. Plaintiff, having executed and returned four copies of a Board of Estimate resolution which expressly recited that commencement date and which had been transmitted with a letter advising that signing the resolution would constitute the lease renewal *904agreement, expressed its intent by its actions. When this execution of the agreement is viewed in…
2Cited by1 opinion
- Bermont Operating Co. v. City of New YorkAppellate Terms of the Supreme Court of New York · 1985