Spring Construction Co. v. Harris
Court of Appeals for the Fourth Circuit
1Opinion of the Court
K. K. HALL, Circuit Judge:
Plaintiff, Spring Construction Company, Inc., brought suit against the Secretary of the Department of Housing and Urban Development (HUD), Parker-Riddick Village, Inc., and Cogic Homes, Inc., seeking damages for breach of contract and equitable relief. After a trial by the court, the district court denied plaintiff any relief and entered judgment for the defendant. Plaintiff appealed. Parker-Riddick Village, Inc., and Cogic Homes, Inc., are not parties in this appeal.
We reverse the judgment of the district court and remand with instructions.
I
FACTS
This suit arose from…
2Cases cited4 opinions
- Trans-Bay Engineers and Builders, Inc. v. Carla A. Hills, Secretary of Housing and Urban DevelopmentCourt of Appeals for the D.C. Circuit · 1976
- American Fidelity Fire Insurance v. Construcciones Werl, Inc.District Court, Virgin Islands · 1975
- Travelers Indemnity Co. v. First National State BankDistrict Court, D. New Jersey · 1971
- Bennett Construction Co. Inc. v. Allen Gardens, Inc.District Court, W.D. Missouri · 1977
3Cited by15 opinions
- Taylor Woodrow Blitman Construction Corp. v. Southfield Gardens Co.District Court, D. Massachusetts · 1982
- Arthur J. Fulcher, Jr. v. United StatesCourt of Appeals for the Fourth Circuit · 1980
- Spring Construction Co. v. HarrisCourt of Appeals for the Fourth Circuit · 1980
- S.S. Silberblatt, Inc. v. East Harlem Pilot Block—Building 1 Housing Development Fund Co.Court of Appeals for the Second Circuit · 1979
- Armor Elevator Co., Inc. v. Phoenix Urban Corp.District Court, D. Massachusetts · 1980