Fargo Cornice & Ornament Co. v. School District No. 88
Supreme Court of Minnesota
1Opinion of the Court
Taylor, O.
Defendant school district let to McDermott & Greenshields the contract to furnish and install the heating plant and ventilating system in a school-house which the district was erecting. The contractors, McDermott & Greenshields, sublet to plaintiff the contract to construct and install the ventilating system. Plaintiff performed its contract and thereafter demanded payment of the contract price from the contractors who failed to pay any part thereof. Defendant had taken a bond from the contractors securing the faithful performance of the contract, but this bond failed to comply with…
2Cases cited8 opinions
- City of Mankato v. Barber Asphalt Paving Co.Court of Appeals for the Eighth Circuit · 1905
- Wilcox Lumber Co. v. School District No. 268Supreme Court of Minnesota · 1907
- Brackett v. RichSupreme Court of Minnesota · 1877
- State ex rel. Morris v. ClarkSupreme Court of Minnesota · 1912
- Manson v. Village of ChisholmSupreme Court of Minnesota · 1919
3 more not listed; retrieve them via the Exa API.
3Cited by4 opinions
- Pelton & King, Inc. v. Town of BethlehemSupreme Court of Connecticut · 1929
- Cahill v. Beltrami CountySupreme Court of Minnesota · 1947
- Green Electric System, Inc. v. Metropolitan Airports CommissionCourt of Appeals of Minnesota · 1992
- Green Electric System, Inc. v. Metropolitan Airports CommissionCourt of Appeals of Minnesota · 1992