Legal Opinion

Alexander v. Fidelity & Casualty Co.

Mississippi Supreme Court

Decided February 3, 1958No. 40618PublishedCited by 16 opinions

1Opinion of the CourtRoberds, P. J.

On December 20, 1954, Jerry G. Alexander entered into a contract with the Mississippi State Highway De partment to construct a certain public road in Covington County, Mississippi. The New Amsterdam and Casualty Company became the surety on the bond of Alexander.

On January 17,1955, Alexander sublet to W. S. Corley & Sons the construction of a certain part of said highway. The Fidelity and Casualty Company of New York became the surety on the contract of Corley.

Corley defaulted in the payment for materials furnished for the construction of said road by two creditors— W. H. Knowles in the sum…

2Cases cited7 opinions

  1. Guerini Stone Co. v. P. J. Carlin Construction Co.Supreme Court of the United States · 1916
  2. Town of Gastonia v. McEntee-Peterson Engineering Co.Supreme Court of North Carolina · 1902
  3. Federal Surety Co. v. Basin Construction Co.Montana Supreme Court · 1931
  4. Fausett Builders, Inc. v. Globe Indemnity Co.Supreme Court of Arkansas · 1952
  5. Mississippi Fire Ins. v. EvansMississippi Supreme Court · 1929

2 more not listed; retrieve them via the Exa API.

3Cited by16 opinions

  1. Grisham v. HintonMississippi Supreme Court · 1986
  2. Tupelo Redevelopment Agency v. AbernathyMississippi Supreme Court · 2005
  3. Urban Masonry Corp. v. N&N Contractors, Inc.District of Columbia Court of Appeals · 1996
  4. Sundown, Inc. v. Canal Square AssociatesDistrict of Columbia Court of Appeals · 1978
  5. Faulkner Concrete Pipe Co. v. United States F. & G. Co.Mississippi Supreme Court · 1968

11 more not listed; retrieve them via the Exa API.

Showing a preview — retrieve the full document via the Exa API.

Powered by the Exa API