WEBBER, Justice.

This was an appeal from an order of the Public Utilities Commission granting a permit to General Marine Construction Corp. to engage in water carrier service limited as follows:

“Irregular Routes. Heavy equipment and material which, because of its size or weight requires the use of a crane-equipped barge in unscheduled service between Portland and (certain islands of Casco Bay) and between said islands.”

The Intervenor Casco Bay Lines, Inc., a water common carrier furnishing scheduled service for the transportation of persons and property between Portland and the islands, has…

2Cases cited6 opinions

  1. United States v. Chemical Foundation, Inc.Supreme Court of the United States · 1926
  2. Morgan v. United StatesSupreme Court of the United States · 1938
  3. Morgan v. United StatesSupreme Court of the United States · 1936
  4. Biddeford and Saco Gas Co. v. Portland Gas Light Co.Supreme Judicial Court of Maine · 1967
  5. Augusta Water District v. WhiteSupreme Judicial Court of Maine · 1966

1 more not listed; retrieve them via the Exa API.

3Cited by2 opinions

  1. New England Telephone & Telegraph Co. v. Public Utilities CommissionSupreme Judicial Court of Maine · 1982
  2. Mechanic Falls Water Co. v. Public Utilities CommissionSupreme Judicial Court of Maine · 1977