Washington Water Power Co. v. Morgan Electric Co.
Montana Supreme Court
1Opinion of the CourtJustice Haswell
Plaintiffs recovered judgment against defendants in the amount of $19,414.01 covering expenditures for a compromise settlement and attorney’s fees in a wrongful death action. The judgment was based on breach of an indemnity agreement in a construction contract which was secured by a performance bond. The case was tried in the district court of Lewis and Clark County before the Honorable Lester H. Loble, district judge, without a jury.
The principal question upon this appeal is the liability of the defendants to indemnify the plaintiffs under the circumstances disclosed here. The trial judge…
2Cases cited4 opinions
- Patent Scaffolding Co. v. William Simpson Construction Co.California Court of Appeal · 1967
- Rae v. CameronMontana Supreme Court · 1941
- Boutwell v. Employers' Liability Assurance Corp.Court of Appeals for the Fifth Circuit · 1949
- Western Construction Equipment Co. v. Mosby's, Inc.Montana Supreme Court · 1965
3Cited by14 opinions
- Tidyman's Manangement Services Inc. v. DavisMontana Supreme Court · 2014
- Luppold v. LewisMontana Supreme Court · 1977
- Compton v. AlcornMontana Supreme Court · 1976
- Arrowhead, Inc. v. Safeway Stores, Inc.Montana Supreme Court · 1978
- Lauterjung v. JohnsonMontana Supreme Court · 1977
9 more not listed; retrieve them via the Exa API.