Brear v. Washington State Highway Commission
Washington Supreme Court
1Opinion of the CourtFinley, J.
Walter Brear, plaintiff-respondent, brought the present action to foreclose a statutory lien for the contract price of crushed rock he supplied to Washington Asphalt Company, defendant-appellant, for use in constructing the approaches to the Hood Canal bridge. The amount due Brear from Washington Asphalt on account of this bridge job (contract #6151) is not in dispute, and Brear has received payment on the amount due, less the sum of $2,934.16, claimed and withheld by Washington Asphalt Company as a setoff. The propriety of the alleged setoff, the principal issue in this appeal, involves…
2Cases cited3 opinions
- Garratt v. DaileyWashington Supreme Court · 1955
- State ex rel. Washington Water Power Co. v. Superior CourtWashington Supreme Court · 1952
- O'Connor v. TesdaleWashington Supreme Court · 1949
3Cited by4 opinions
- Nakanishi v. FosterWashington Supreme Court · 1964
- Brear v. Washington State Highway CommissionWashington Supreme Court · 1965
- Reilly v. SageserCourt of Appeals of Washington · 1970
- S & D Paving Co. v. Douglas CountyWashington Supreme Court · 1967