Opinion No.
Texas Attorney General Reports
1Opinion of the Court
Honorable Mack Wallace Chairman Railroad Commission of Texas P.O. Drawer 12967 Austin, Texas 78711
Re: Construction of section 5.02(b) of article 1446e, V.T.C.S., the Public Utility Regulatory Act
Dear Mr. Wallace:
You have asked whether section 5.02(b) of article 1446e, V.T.C.S., the Gas Utility Regulatory Act [hereinafter GURA], precludes the Railroad Commission from investigating the reasonableness of a change in rates between pipelines in instances in which the change will directly or indirectly affect a city gate rate. We conclude that you are not so precluded. We conclude that the…
2Cases cited8 opinions
- Railroad Commission of Texas v. MillerTexas Supreme Court · 1968
- State v. JacksonTexas Supreme Court · 1964
- American Surety Co. of New York v. Axtell Co.Texas Supreme Court · 1931
- Anderson v. PenixTexas Supreme Court · 1942
- Texas Turnpike Authority v. ShepperdTexas Supreme Court · 1955
3 more not listed; retrieve them via the Exa API.