Error to the Court of Common Pleas of Blair county: Of May Term 1875, No. 66. This was an action of assumpsit, brought to the July Term 1873 of the court below, by Josiah M. Christy against The Bell’s Gap Railroad Company.
Read the full summary
Error to the Court of Common Pleas of Blair county: Of May Term 1875, No. 66. This was an action of assumpsit, brought to the July Term 1873 of the court below, by Josiah M. Christy against The Bell’s Gap Railroad Company. The suit was brought to recover money expended by plaintiff in procuring the charter of the defendants, in payment of surveyors, &c., in making explorations and running the line of their road, &c., and also for his own services in the same matter; the whole occurred before the corporation came into existence, but plaintiff claimed that the defendants having accepted the…
1Opinion of the CourtJustice Paxson
*58This case lacks all the elements of a contract, either express or implied. The most that it amounts to is the expenditure by the plaintiff of a certain amount of his time and money in the furtherance of a scheme of constructing a railroad. He attended meetings ; visited Harrisburg for the purpose of obtaining a charter; assisted in making a preliminary survey, and paid some of the expenses thereof. There was no contract with any one for the payment of his services, beyond the statement of some of the parties interested in the project that they would see him paid. All this was prior to the…
2Cited by9 opinions
- Hinkley v. Sac Oil & Pipe Line Co.Supreme Court of Iowa · 1906
- Girard v. Case Bros. Cutlery Co.Supreme Court of Pennsylvania · 1909
- Bonner v. Travelers Hotel Co.Supreme Court of Pennsylvania · 1923
- Tift v. Quaker City N. BankSupreme Court of Pennsylvania · 1891
- Tanner v. Sinaloa Land & Fruit Co.Utah Supreme Court · 1913
4 more not listed; retrieve them via the Exa API.