Legal Opinion · Dissent

National Surety Corp. v. United States

United States Court of Claims

Decided December 4, 1944No. 45797Published

1DissentLittleton, Judge

The question presented in this case is whether under the provisions of art. 9 of the contract the Government is entitled to liquidated damages *682for delay until completion of the work called for by the contract; and, also, the actual excess costs of completing the contract, when the contractor without any action by or fault on the part of the Government discontinued work thereunder and notified the Government, upon being ordered to proceed with the work and prosecute it to completion, that it could not continue with and prosecute the work or any part thereof to completion. Under that article…

2Cases cited10 opinions

  1. United States v. United States Fidelity & Guaranty Co.Supreme Court of the United States · 1915
  2. Philadelphia, Wilmington & Baltimore Railroad v. HowardSupreme Court of the United States · 1852
  3. United States v. American Surety Co.Supreme Court of the United States · 1944
  4. Modern Industrial Bank v. United StatesUnited States Court of Claims · 1944
  5. Quinn v. United StatesSupreme Court of the United States · 1879

5 more not listed; retrieve them via the Exa API.

Showing a preview — retrieve the full document via the Exa API.

Powered by the Exa API