Legal Opinion

Millimet Construction Co. v. United States

United States Court of Claims

Decided May 2, 1949No. 46130Published

1Opinion of the CourtLittleton, Judge

Plaintiff entered into a contract with defendant March 10, 1938, for the remodeling of the Grand Central Annex Post Office Building in New York City, for a lump sum consideration of $1,849,000. The original period for completion of the work was 360 calendar days after March 24, 1938. The period so fixed expired March 19, 1939. The defendant took possession of the substantially completed work on April 14,1940. The defendant was liberal in granting extensions of time. Extensions of time totaling 396 days were granted which extended the completion date to April 18, 1940. Of these extensions, 253…

2Cases cited4 opinions

  1. United States v. Callahan Walker Construction Co.Supreme Court of the United States · 1942
  2. James Stewart & Co. v. United StatesUnited States Court of Claims · 1946
  3. Magoba Construction Co. v. United StatesUnited States Court of Claims · 1943
  4. Olson Construction Co. v. United StatesUnited States Court of Claims · 1948

Showing a preview — retrieve the full document via the Exa API.

Powered by the Exa API