Legal Opinion

National Equipment Corp. v. Pinnell

West Virginia Supreme Court

Decided January 23, 1934No. 7619PublishedCited by 3 opinions

1Opinion of the Court

Hatcher, Judge :

This appeal involves the obligation of principal contractors and their surety to pay the balance due from subcontractors for machinery used on the work, for repairs on the machinery, and for other mechanical supplies.

About the first of June, 1931, defendants Pinnell & Pfost contracted with the State Road Commission to grade a certain roadway and executed a bond with defendant American Surety Company as surety. Shortly afterwards defendants K. J. Smith & Son were given a subcontract to perform part of the grading. The Smiths then purchased from plaintiff National Equipment…

2Cases cited4 opinions

  1. Hicks v. RandichWest Virginia Supreme Court · 1928
  2. Liberty Coal Co. v. BassettWest Virginia Supreme Court · 1929
  3. Rhodes v. RileyWest Virginia Supreme Court · 1933
  4. Lefever v. ThomasWest Virginia Supreme Court · 1911

3Cited by3 opinions

  1. American Liability & Surety Co. v. Bluefield Supply Co.Court of Appeals for the Fourth Circuit · 1934
  2. Bluefield Supply Co. v. M. P. Smith Construction Co.West Virginia Supreme Court · 1934
  3. Cecil I. Walker MacHinery Co. v. Stauben, Inc.West Virginia Supreme Court · 1976

Showing a preview — retrieve the full document via the Exa API.

Powered by the Exa API