Wheeling Steel Corp. v. United States
United States Court of Claims
1Opinion of the CourtLittleton, Judge
The defendant has filed a motion for a new trial asking for certain amendments and additions to the findings of fact heretofore made and urging that the amount of $43,234.28, representing the difference between the cost of the raw materials and their market value at the date of cancellation of the contracts, be allowed in determining the just compensation to which the plaintiff is entitled instead of the amount of $64,832.77 heretofore allowed by the court.
Upon consideration of this motion, the court is of opinion that it is well taken, and it is allowed. The findings of fact, conclusion of…