Boeing Co. v. United States
United States Court of Claims
1Opinion of the Court
OPINION AND ORDER
ROBINSON, Judge:
This matter is before the court on defendant’s motion to dismiss for lack of subject matter jurisdiction pursuant to RUSCC 12(b)(1), and defendant’s opposition to plaintiff's filing of a first amended complaint. Plaintiff, The Boeing Company (Boeing), seeks to retain $605,424,954.50 in progress payments paid by defendant prior to the partial termination for default of Contract No. F19628-85-C-0046 (contract), and various other payments allegedly due under the contract. Alternatively, plaintiff seeks a judgment converting the termination into one for…
2Cases cited13 opinions
- United States v. KingSupreme Court of the United States · 1969
- Mollan v. TorranceSupreme Court of the United States · 1824
- Smith v. SperlingSupreme Court of the United States · 1957
- Placeway Construction Corporation v. The United StatesCourt of Appeals for the Federal Circuit · 1990
- Paragon Energy Corp. v. United StatesUnited States Court of Claims · 1981
8 more not listed; retrieve them via the Exa API.
3Cited by5 opinions
- Fairchild Industries, Incorporated v. United StatesCourt of Appeals for the Federal Circuit · 1996
- Boeing Co. v. United StatesUnited States Court of Federal Claims · 1994
- McDonnell Douglas Corp. v. United StatesUnited States Court of Federal Claims · 1997
- Boeing Co. v. United StatesUnited States Court of Claims · 1992
- Hamilton Securities Advisory Services, Inc. v. United StatesUnited States Court of Federal Claims · 1999