Thomas Industries, Inc v. C & L Electric, Inc
Michigan Court of Appeals
1Per curiam
Plaintiff appeals as of right an order granting summary disposition pursuant to MCR 2.116(C)(10) for defendants. The trial court held that, under § 7 of the relevant public works construction bond act, MCL 129.207; MSA 5.2321(7), plaintiffs failure to satisfy the statutory notice requirements precluded it from recovering $17,473.05 against the payment bond defendant C & L Electric, Inc., procured through defendant United States Fidelity and Guaranty Company (usf&g). Defendants cross appeal, arguing that the court erred in denying their motion for costs and attorney fees. We affirm.
The facts…
2Cases cited4 opinions
- Fleisher Engineering & Construction Co. v. United States Ex Rel. HallenbeckSupreme Court of the United States · 1940
- Kammer Asphalt Paving Co. v. East China Township SchoolsMichigan Supreme Court · 1993
- Pi-Con, Inc. v. a J Anderson Construction Co.Michigan Supreme Court · 1990
- Milbrand Co. v. Department of Social ServicesMichigan Court of Appeals · 1982
3Cited by6 opinions
- Wyandotte Electric Supply Co. v. Electrical Technology Systems, Inc.Michigan Supreme Court · 2016
- Grand Blanc Cement Products, Inc. v. Insurance Co. of North AmericaMichigan Court of Appeals · 1997
- Bearing360 LLC v. Larry CameronMichigan Court of Appeals · 2017
- Bearing360 LLC v. Larry CameronMichigan Court of Appeals · 2017
- Grand Blanc Cement v. INAMichigan Court of Appeals · 1997