Pacific Maritime Ass'n v. United States
United States Court of Claims
1Opinion of the CourtWhitakee, Judge
Defendant files a motion for a rehearing on the ground that our decision in this case is in conflict with our decision in Luff v. United States, 120 C. Cls. 682.
The gist of our holding in that case was that where a contractor allows the 90 days to elapse from the findings of the contracting agency without having appealed to the Appeal Board, or without having brought suit in this court, he is barred from doing so later on the theory that, independent of the Contract Settlement Act, he has a claim coming within our general jurisdiction. We did no more in that case than to reject the…
2Cases cited1 opinion
- Luff v. United StatesUnited States Court of Claims · 1951
3Cited by1 opinion
- Mega Construction Co. v. United StatesUnited States Court of Federal Claims · 1993