Petersen v. HUBSCHMAN CONST. CO., INC.
Appellate Court of Illinois
1Opinion of the Court
Mr. PRESIDING JUSTICE RECHENMACHER
delivered the opinion of the court:
The Petersens entered into a contract with Hubschman Construction Co., Inc. (hereafter “Hubschman”), for the construction and purchase of a new home. The contract also provided that the Petersens were to receive a credit (on the contract price of *71,400) for plumbing and other work which was to be done by Mr. Petersen, who was a heating and plumbing contractor. After the home was nearly complete, a dispute arose concerning certain aspects of the construction which the Petersens contended were unfinished or unsatisfactory, and…
2Cases cited4 opinions
- Brewer v. Custom Builders Corp.Appellate Court of Illinois · 1976
- Watson Lumber Co. v. MouserAppellate Court of Illinois · 1975
- Goggin v. Fox Valley Construction Corp.Appellate Court of Illinois · 1977
- Kobus v. Jefferson Ice Co.Appellate Court of Illinois · 1971
3Cited by2 opinions
- Petersen v. Hubschman Construction Co.Illinois Supreme Court · 1979
- Kramp v. Showcase BuildersAppellate Court of Illinois · 1981