Legal Opinion
Engineer Co. v. Herring-Hall, Marvin Safe Co.
New York Supreme Court
Decided April 15, 1912PublishedCited by 2 opinions
Action for breach of contract.
1Opinion of the Court
¡Newburger, J.
After some negotiations and correspondence Between the parties, the defendant, By its authorized officer, signed a contract whereby the plaintiff was to install a draft system in the defendant’s boiler room. .Accompanying 'the contract the defendant sent a letter to the plaintiff as follows:
¡New York,. April 30, 1908.
“ The Engineer Co., Mr. ¡R. E. Fox, Jr., Secretary, Trinity Building, Oity:
“ Gentlemen.— I enclose herewith signed contract for the installation of your .balanced draft system in our Hamilton, Ohio-, power plant, specified in you,r proposal of recent date, this to…
2Cases cited1 opinion
- People v. . GluckNew York Court of Appeals · 1907
3Cited by2 opinions
- Johnsen v. HaynieCourt of Appeals of Texas · 1934
- McElraevy & Hauck Co. v. St. Joseph's Home for GirlsCity of New York Municipal Court · 1913