Central Ceilings, Inc. v. Suffolk Construction Co., Inc.
Massachusetts Appeals Court
1Opinion of the CourtDitkoff, J.
*207 The parties submitted a construction dispute, pending in litigation in the Superior Court, to arbitration under the Uniform Arbitration Act, G. L. c. 251, §§ 1 et seq. The arbitrator issued a substantial award in favor of the plaintiff, Central Ceilings, Inc., but purported to reserve the calculation of preaward *208 interest to a Superior Court judge. The parties did not agree to this reservation. On the plaintiff's motion *940 to confirm the arbitration award, the judge (remanding judge) remanded the matter to the arbitrator for the calculation of preaward interest. After the arbitrator awarded…
2Cases cited21 opinions
- Plymouth-Carver Regional School District v. J. Farmer & Co.Massachusetts Supreme Judicial Court · 1990
- City of Lynn v. ThompsonMassachusetts Supreme Judicial Court · 2001
- Floors, Inc. v. B. G. Danis of New England, Inc.Massachusetts Supreme Judicial Court · 1980
- Murphy v. National Union Fire InsuranceMassachusetts Supreme Judicial Court · 2003
- Sansone v. Metropolitan Property & Liability InsuranceMassachusetts Appeals Court · 1991
16 more not listed; retrieve them via the Exa API.