United States Pipe & Foundry Co. v. Goerig
Washington Supreme Court
1Opinion of the CourtSchwellenbach, J.
— This is an appeal from judgments dismissing an action, after demurrers to the complaint had been sustained, the plaintiffs having elected to stand upon their complaint.
The complaint alleged the entering into of a contract on July 14, 1945, between Goerig & Philp and the city of Sunnyside, whereby Goerig & Philp agreed to construct a sewage disposal plant for the city for the agreed contract price of $157,613.40; that between August 1, 1945, and April 13, 1946, plaintiffs furnished supplies to the contractors, on which there is a balance owing and.unpaid of $7,098.72; that said supplies were…
2Cases cited6 opinions
- Denny-Renton Clay & Coal Co. v. National Surety Co.Washington Supreme Court · 1916
- Puget Sound Bridge & Dredging Co. v. Jahn & BressiWashington Supreme Court · 1928
- John Dower Lumber Co. v. New Amsterdam Casualty Co.Washington Supreme Court · 1929
- McGowan Bros. Hardware Co. v. Fidelity & Deposit Co. of MarylandWashington Supreme Court · 1915
- Union High School District No. 400 v. Pacific Northwest Construction Co.Washington Supreme Court · 1928
1 more not listed; retrieve them via the Exa API.
3Cited by1 opinion
- National Blower & Sheet Metal Co. v. American Surety Co.Washington Supreme Court · 1952