FIRESTONE, Judge.

The present post-award bid protest was filed under 28 U.S.C. § 1491(b)(1) (2000). At issue is a Request for Proposal (“RFP”) for a small business set-aside task order (“task order”) to provide maintenance of flight' simulation equipment to the United States Air Force (“Air Force”). The RFP was issued pursuant to a multi-award Indefinite Delivery/Indefinite Quantity (“ID/IQ”) contract previously awarded by the Air Force in 2001. The underlying ID/IQ contract, known as Training Systems Acquisition II (“TSA II contract”), authorized the Air Force to issue task orders for…

2Cases cited11 opinions

  1. McNutt v. General Motors Acceptance Corp.Supreme Court of the United States · 1936
  2. United States v. MitchellSupreme Court of the United States · 1980
  3. McCarthy v. MadiganSupreme Court of the United States · 1992
  4. John D. Holley v. United StatesCourt of Appeals for the Federal Circuit · 1997
  5. Baird Corp. v. United StatesUnited States Court of Claims · 1983

6 more not listed; retrieve them via the Exa API.

3Cited by15 opinions

  1. Precise Systems, Inc. v. United StatesUnited States Court of Federal Claims · 2015
  2. Lukos Vatc Jv LLC v. United StatesUnited States Court of Federal Claims · 2014
  3. Palladian Partners, Inc. v. United StatesUnited States Court of Federal Claims · 2014
  4. 22nd Century Technologies, Inc. v. United StatesUnited States Court of Federal Claims · 2021
  5. Defense Integrated Solutions, LLC v. United StatesUnited States Court of Federal Claims · 2023

10 more not listed; retrieve them via the Exa API.

Showing a preview — retrieve the full document via the Exa API.

Powered by the Exa API