Trinity Universal Insurance Company v. Charles L. Girdner, D/B/A Girdner Electric & Refrigeration Service
Court of Appeals for the Fifth Circuit
1Per curiam
The Miller Act statute of limitations provides that no subcontractor may commence suit against the Miller Act surety “after the expiration of one year after the day on which the last of the labor was performed or material was supplied by him.” 40 U.S.C. § 270b (b).
In this case the only work done by the subcontractor within the year before the commencement of suit was to replace some defective pipe insulation which he had previously installed and to replace a seal in an air conditioning unit. The subcontractor performed these operations on the demand of the government inspector, who refused to…
2Cases cited4 opinions
- Illinois Surety Co. v. John Davis Co.Supreme Court of the United States · 1917
- United States v. Western Electric Co.Court of Appeals for the Ninth Circuit · 1964
- United States Ex Rel. McGregor Architectural Iron Co. v. Merritt-Chapman & Scott Corp.District Court, M.D. Pennsylvania · 1960
- United States ex rel. Circle-L-Electric Co. v. Hyde Construction Co.District Court, N.D. Oklahoma · 1966
3Cited by25 opinions
- Johnson Service Company v. Transamerica Insurance CompanyCourt of Appeals for the Fifth Circuit · 1973
- United States of America for the Use of Georgia Electric Supply Company, Inc. v. United States Fidelity and Guaranty CompanyCourt of Appeals for the Fifth Circuit · 1981
- Graybar Electric Company, Inc. v. John A. Volpe Construction Co., Inc.Court of Appeals for the Fifth Circuit · 1967
- Valley Forge Industries, Inc. v. Armand Construction, Inc.Commonwealth Court of Pennsylvania · 1978
- General Insurance Company of America v. United States for the Use of Audley Moore & SonCourt of Appeals for the Fifth Circuit · 1969
20 more not listed; retrieve them via the Exa API.