McDonough v. General Motors Corp.
Michigan Court of Appeals
1Opinion of the CourtMahinske, J.
This appeal arises from the determination of the trial court during the course of trial that plaintiff had neither alleged nor proven a cause of action against General Motors.
Paragon Bridge and Steel Company held the steel fabrication subcontract in the construction of an addition to General Motors’ Chevrolet assembly plant in Flint. Michael McDonough, plaintiff’s decedent, was employed by Paragon on the project. On October 3, 1963, he was a member of Paragon’s crew tying the boom of Paragon’s stiff-legged derrick to a permanent truss in order to secure it for the night. The boom fell,…
2Cases cited3 opinions
- Vannoy v. City of WarrenMichigan Court of Appeals · 1968
- Dees v. L. F. Largess Co.Michigan Court of Appeals · 1965
- Royal v. McNultyMichigan Court of Appeals · 1969
3Cited by6 opinions
- Wilhelm v. Detroit Edison Co.Michigan Court of Appeals · 1974
- McDonough v. General Motors Corp.Michigan Supreme Court · 1973
- People v. HudsonMichigan Supreme Court · 1972
- Fecteau v. Wolco Homes, Inc.Michigan Court of Appeals · 1971
- McDonough v. General Motors Corp.Michigan Supreme Court · 1973
1 more not listed; retrieve them via the Exa API.