This cause is pending before the Court on the appellee’s Motion to Dismiss or Affirm Judgment of Trial Court which alleges inter alia, that the motion to correct errors was not timely filed within sixty days after the judgment was entered. The crux of the problem raised by appellee’s motion is whether the filing of the motion to correct errors can be accomplished by mailing as provided for by Rule TR. 5(E).
The record reveals that judgment was entered on July 17, 1972. Sixty days from July 17 fell on September 15. On September 15, a Friday, Appellants’ counsel mailed the motion to correct…
2Cases cited8 opinions
- Burch v. Grace Street Building Corp.Supreme Court of Virginia · 1937
- Treadgold v. WillardOregon Supreme Court · 1916
- Landrum v. StateCourt of Criminal Appeals of Oklahoma · 1953
- Parliman v. YoungSupreme Court Of The Territory Of Dakota · 1879
- Hong Sling v. National Assurance Co.Utah Supreme Court · 1891
3 more not listed; retrieve them via the Exa API.
3Cited by10 opinions
- State Exchange Bank of Culver v. TeagueIndiana Court of Appeals · 1986
- Data Processing Services, Inc. v. L.H. Smith Oil Corp.Indiana Court of Appeals · 1986
- Cooper v. StateIndiana Court of Appeals · 1999
- Unishops, Inc. v. May's Family Centers, Inc.Indiana Court of Appeals · 1978
- Baker v. StateIndiana Court of Appeals · 1987
5 more not listed; retrieve them via the Exa API.