Consolidated Edison Co. of New York, Inc. v. 1297 Realty Corp.
Civil Court of the City of New York
1Opinion of the Court
OPINION OF THE COURT
David B. Saxe, J.
In a Civil Court action that is subject to mandatory arbitration, must a party, in order to preserve his right to a jury trial, submit a jury demand at or within 10 days of the time the notice of trial is served, or can he wait until the time of service of the demand for a trial de novo (or within 10 days thereafter)?
The plaintiff, Con Edison, commenced this action to recover gas and electric charges from the defendant. Thereafter, a notice of trial pursuant to CCA 1301 was served by the plaintiff. Neither side filed a demand for a trial by jury at that…
2Cases cited4 opinions
- Duncan v. LouisianaSupreme Court of the United States · 1968
- Asbestolith Manufacturing Co. v. HowlandAppellate Division of the Supreme Court of the State of New York · 1911
- Jefferson Pulp & Paper, Inc. v. ArringtonCivil Court of the City of New York · 1974
- Litoff v. RutelAppellate Division of the Supreme Court of the State of New York · 1966
3Cited by2 opinions
- Lehrman Kronick & Lehrman v. MancusoWhite Plains City Court · 1990
- Seminerio Associates Inc. v. Brownstone Solutions, Inc.Civil Court of the City of New York · 1995