Dutt v. Duvall
Nevada Supreme Court
1Opinion of the Court
OPINION
2Per curiam
Appellant Virgil Dutt is the assignee of a garage construction contract between Storey Improvement Company (Storey) and respondent Blanche Duvall. The original contract price was $2,800, with a down payment of $300 by Duvall, and the balance to be financed.
After a trial before the court, the district judge found that Storey, as part financing, had borrowed $1,900 from the Nevada National Bank, that it proceeded to construct the garage and did so in a workman-like manner, and that the garage was constructed according to the contract between the parties. A lien of $1,045 was placed on…
3Cases cited1 opinion
- Fuller v. United Electric Co.Nevada Supreme Court · 1954