Csc Government Solutions LLC v. United States
United States Court of Federal Claims
1Opinion of the Court
Post-award bid protest of an IT contract; cost-realism analysis; application of FAR § 52.222-46 to realism of proposed salaries with regard to program continuity, retention of professional employees, and “uninterrupted high-quality work;” consistency of the agency’s cost-price and technical evaluations; past performance evaluation; discussions
OPINION AND ORDER 1
LETTOW, Judge
This post-award bid protest arises from a solicitation by the United States Department of the Air Force, United States Strategic Command (“USSTRATCOM” or “government”) for the Information Technology Capabilities Contract…
2Cases cited42 opinions
- Motor Vehicle Mfrs. Assn. of United States, Inc. v. State Farm Mut. Automobile Ins. Co.Supreme Court of the United States · 1983
- Citizens to Preserve Overton Park, Inc. v. VolpeSupreme Court of the United States · 1971
- Califano v. SandersSupreme Court of the United States · 1977
- Burlington Truck Lines, Inc. v. United StatesSupreme Court of the United States · 1962
- Bannum, Inc. v. United StatesCourt of Appeals for the Federal Circuit · 2005
37 more not listed; retrieve them via the Exa API.
3Cited by23 opinions
- Agile Defense, Inc. v. United StatesUnited States Court of Federal Claims · 2019
- Appsential, LLC v. United StatesUnited States Court of Federal Claims · 2021
- Bowhead Enterprise, Science and Technology, LLC v. United StatesUnited States Court of Federal Claims · 2025
- Englobal Government Services, Inc. v. United StatesUnited States Court of Federal Claims · 2022
- Gritter-Francona, Inc v. United StatesUnited States Court of Federal Claims · 2022
18 more not listed; retrieve them via the Exa API.