In re the Arbitration between Morrow & General Accident Fire & Life Assurance Corp.
Appellate Division of the Supreme Court of the State of New York
1Opinion of the Court
The facts and the legal issues arising upon them are well outlined and defined in the comprehensive opinion of Mr. Justice Main at Special Term. It is clear that the arbitrators’ powers were “so imperfectly executed * * * that a * * * definite award upon the subject-matter submitted was not made”. (Civ. Prac. Act, § 1462, subd. 4.) In consequence, the vacatur and resubmission were proper, as was the confirmation of the amended award. (Matter of Zephyr Gonstr. Go. [Boro Hall Corp.], 7 A D 2d 915 and cases cited p. 916, second appeal 10 A D 2d 867; 21 Carmody-Wait, New York Practice, §§ 170,…
2Cited by1 opinion
- Herman v. CuperoAppellate Division of the Supreme Court of the State of New York · 2004