Entergy Gulf States, Inc. v. United States
United States Court of Federal Claims
1Opinion of the Court
Spent Nuclear Fuel; Partial Breach of Contract; Damages; Causation; Cask Loading Costs.
OPINION AND ORDER ENTERING PARTIAL JUDGMENT
WILLIAMS, Judge.
This opinion is a continuation of the Court’s prior decision in Entergy Gulf States, Inc. v. United States, 125 Fed.Cl. 678 (2016), which deferred one claim pending the decision of the United States Court of Appeals for the Federal Circuit in System Fuels, Inc. v. United States, 818 F.3d 1302 (Fed.Cir.2016). Following a 12-day trial beginning in 2015, this Court awarded Plaintiffs a partial judgment of $42,341,604 in damages for site modifications,…
2Cases cited2 opinions
- System Fuels, Inc. v. United StatesCourt of Appeals for the Federal Circuit · 2016
- Entergy Gulf States, Inc. v. United StatesUnited States Court of Federal Claims · 2016
3Cited by3 opinions
- Entergy Louisiana, L.L.C. v. United StatesUnited States Court of Federal Claims · 2017
- Entergy Gulf States, Inc. v. United StatesUnited States Court of Federal Claims · 2017
- Entergy Gulf States, Inc. v. United StatesUnited States Court of Federal Claims · 2016