This is an interlocutory appeal from an order of the trial court denying a motion to stay proceedings and to compel arbitration.

On October 17, 1978, plaintiff, Kelso-Burnett Co. (hereinafter “Kelso”), entered into a subcontract with the general contractor of the Briar-wood Lakes project in Oak Brook, defendant Zeus Development Corporation (hereinafter “Zeus”), wherein Kelso agreed to perform electrical work for the project. The contract included an arbitration clause which provided that:

“Unless otherwise agreed, all claims, disputes, and other matters in question arising out of, or relating…

2Cases cited14 opinions

  1. Garrity v. Lyle Stuart, Inc.New York Court of Appeals · 1976
  2. Flood v. Country Mutual InsuranceIllinois Supreme Court · 1968
  3. School District No. 46 v. Del BiancoAppellate Court of Illinois · 1966
  4. S & F CORP. v. American Express Co.Appellate Court of Illinois · 1978
  5. J. F. Inc. v. VicikAppellate Court of Illinois · 1981

9 more not listed; retrieve them via the Exa API.

3Cited by25 opinions

  1. J&K Cement Construction, Inc. v. Montalbano Builders, Inc.Appellate Court of Illinois · 1983
  2. Kostakos v. KSN Joint Venture No. 1Appellate Court of Illinois · 1986
  3. Yates v. Doctor's Associates, Inc.Appellate Court of Illinois · 1990
  4. Board of Managers of the Courtyards at the Woodlands Condominium Ass'n v. Iko Chicago, Inc.Illinois Supreme Court · 1998
  5. Village of Mundelein v. HartnettAppellate Court of Illinois · 1983

20 more not listed; retrieve them via the Exa API.

Showing a preview — retrieve the full document via the Exa API.

Powered by the Exa API