Legal Opinion

LeGrand Johnson Construction Co. v. Kennedy

Utah Supreme Court

Decided October 31, 1975No. 14038PublishedCited by 1 opinion

1Opinion of the Court

TUCKETT, Justice:

Plaintiff initiated these proceedings for the purpose of foreclosing a lien pursuant to the provisions of Section 38-1-11, U.C. A.1953. The plaintiff supplied concrete which was used in the construction of a home built for the defendants, together with certain work performed in relation thereto. From an adverse judgment in the District Court of Cache County, plaintiff is here seeking a reversal.

On or about September 24, 1971, the defendants contracted with one Zan Longs-troth to build a home on property owned by the defendants. Plaintiff furnished ready-mix concrete used in…

2Cases cited3 opinions

  1. Holbrook v. Webster's Inc.Utah Supreme Court · 1958
  2. Brimwood Homes, Inc. v. Knudsen Builders Supply Co.Utah Supreme Court · 1963
  3. Zions First National Bank v. SaxtonUtah Supreme Court · 1972

3Cited by1 opinion

  1. Neiderhauser Builders & Development Corp. v. CampbellCourt of Appeals of Utah · 1992