R. G. R. Construction Corp. v. Robert J. Harder, Inc.
New York Supreme Court
1Opinion of the CourtNicholas M. Pette, J.
This is an application by a general contractor to stay a subcontractor from proceeding “ except through arbitration.” In effect the movant seeks to vacate a notice of mechanic’s lien which was filed by the subcontractor when the contract between the parties provides that such subcontractor “ waives and releases the filing of any lien or claims and all right of lien now existing or that may hereafter arise for Work or labor performed or materials furnished under this contract * * * ” and there is a provision for arbitration of ‘ ‘ Any dispute or claim arising out of, or relating to this…
2Cases cited1 opinion
- May v. New Amsterdam Casualty Co.Appellate Division of the Supreme Court of the State of New York · 1946
3Cited by2 opinions
- Mancini v. SternNew York Supreme Court · 1960
- Joseph P. Blitz, Inc. v. Di Cesare & Monaco Building Co.New York Supreme Court · 1962