Dart Mechanical Corp. v. City of New York
Appellate Division of the Supreme Court of the State of New York
1Opinion of the Court
Plaintiff failed to meet its heavy burden of establishing that the 32-month delay in the construction project falls within an exception to the rule that a “no damages for delay” clause in a construction contract such as the instant contract will be enforced (see Corinno Civetta Constr. Corp. v City of New York, 67 NY2d 297 [1986]; Kalisch-Jarcho, Inc. v City of New York, 58 NY2d 377 [1983]; North Star Contr. Corp. & Tern Star v City of New York, 203 AD2d 214 [1994]).
The record shows that the primary responsibility for the delay lay with another contractor, that defendants retained a…
2Cases cited6 opinions
- Kalisch-Jarcho, Inc. v. City of New YorkNew York Court of Appeals · 1983
- Corinno Civetta Construction Corp. v. City of New YorkNew York Court of Appeals · 1986
- Buckley & Co. v. City of New YorkAppellate Division of the Supreme Court of the State of New York · 1986
- North Star Contracting Corp. v. City of New YorkAppellate Division of the Supreme Court of the State of New York · 1994
- MRW Construction Co. v. City of New YorkAppellate Division of the Supreme Court of the State of New York · 1996
1 more not listed; retrieve them via the Exa API.
3Cited by5 opinions
- Travelers Casualty & Surety Co. v. Dormitory Authority-StateDistrict Court, S.D. New York · 2010
- LoDuca Associates, Inc. v. PMS Construction Management Corp.Appellate Division of the Supreme Court of the State of New York · 2012
- Plato General Construction Corp./EMCO Tech Construction Corp. JV, LLC v. Dormitory AuthorityAppellate Division of the Supreme Court of the State of New York · 2011
- Gamma USA, Inc. v. Pavarini McGovern, LLCAppellate Division of the Supreme Court of the State of New York · 2025
- Welsbach Elec. Corp. v. Judlau Contr., Inc.Appellate Division of the Supreme Court of the State of New York · 2019