McParlin v. Thompson
Supreme Court of Rhode Island
Mechanic's Lien.
1Per curiam
It appears from the testimony of the petitioner that the materials for which he claims a lien were delivered under an entire contract made November 14, 1894, and that delivery thereunder began November 15, 1894. Legal process for the enforcement of the lien was commenced on the fifth day of June, 1895. As this was more than six months from the time of the commencing the delivery of materials, it was not a compliance with the provisions of the statute governing the same, Pub. Laws, It. I. cap. 696, § 4, passed March 21,1888, which is necessary for the enjoyment of its privileges. The statute…