Legal Opinion

Maroney v. Friere

New York Supreme Court

Decided May 3, 1973PublishedCited by 8 opinions

1Opinion of the CourtJohn W. Sweeny, J.

By this article 78 proceeding petitioners seek a judgment annulling the respondent board’s determination whereby it rejected their notice of appeal as untimely and thereby upheld the issuance of a building permit to respondents Ashley.

The permit in question was issued by the building inspector on November 28,1972. Petitioners, neighboring landowners, did not file their notice of appeal with the Zoning Board of Appeals until April 4,1973, some 127 days after the issuance of the permit and after the Ashleys had entered into a building contract.

On April 9, 1973 the Board of Appeals notified…

2Cited by8 opinions

  1. Goto v. District of Columbia Board of Zoning AdjustmentDistrict of Columbia Court of Appeals · 1980
  2. Cave v. Zoning Board of AppealsAppellate Division of the Supreme Court of the State of New York · 1975
  3. Keating v. Zoning Board of Appeals of City of SacoSupreme Judicial Court of Maine · 1974
  4. Woodley Park Community Ass'n v. District of Columbia Board of Zoning AdjustmentDistrict of Columbia Court of Appeals · 1985
  5. Georgetown Residents Alliance v. District of Columbia Board of Zoning AdjustmentDistrict of Columbia Court of Appeals · 2003

3 more not listed; retrieve them via the Exa API.

Showing a preview — retrieve the full document via the Exa API.

Powered by the Exa API