City of Florence v. Powder Horn Constructors, Inc.

Colorado Court of Appeals

Decided October 17, 1985No. 83CA0690PublishedCited by 3 opinions

1Opinion of the Court

BABCOCK, Judge.

On this issue of first impression in Colorado, we must decide whether a contractor may be relieved of its bid on a public construction project where the bid is the product of a clerical error and the public authority is notified of the error prior to the award of the contract. We hold that relief from a bid is possible, but that the contractor bears the burden of proving by a preponderance of the evidence that: (1) the mistake relates to a material feature of the contract; (2) it occurred despite the exercise of reasonable care; and (3) the public authority can be placed in…

2Cases cited17 opinions

  1. Page v. ClarkSupreme Court of Colorado · 1979
  2. Moffett, Hodgkins & Clarke Co. v. RochesterSupreme Court of the United States · 1900
  3. John J. Calnan Co. v. Talsma Builders, Inc.Illinois Supreme Court · 1977
  4. Colella v. Allegheny CountySupreme Court of Pennsylvania · 1958
  5. Board of Edn. v. Sever-Williams Co.Ohio Supreme Court · 1970

12 more not listed; retrieve them via the Exa API.

3Cited by3 opinions

  1. Powder Horn Constructors, Inc. v. City of FlorenceSupreme Court of Colorado · 1988
  2. Powder Horn Constructors, Inc. v. City of FlorenceSupreme Court of Colorado · 1988
  3. Powder Horn Constructors, Inc. v. City of FlorenceSupreme Court of Colorado · 1988

Showing a preview — retrieve the full document via the Exa API.

Powered by the Exa API