City of Florence v. Powder Horn Constructors, Inc.
Colorado Court of Appeals
1Opinion of the Court
BABCOCK, Judge.
On this issue of first impression in Colorado, we must decide whether a contractor may be relieved of its bid on a public construction project where the bid is the product of a clerical error and the public authority is notified of the error prior to the award of the contract. We hold that relief from a bid is possible, but that the contractor bears the burden of proving by a preponderance of the evidence that: (1) the mistake relates to a material feature of the contract; (2) it occurred despite the exercise of reasonable care; and (3) the public authority can be placed in…
2Cases cited17 opinions
- Page v. ClarkSupreme Court of Colorado · 1979
- Moffett, Hodgkins & Clarke Co. v. RochesterSupreme Court of the United States · 1900
- John J. Calnan Co. v. Talsma Builders, Inc.Illinois Supreme Court · 1977
- Colella v. Allegheny CountySupreme Court of Pennsylvania · 1958
- Board of Edn. v. Sever-Williams Co.Ohio Supreme Court · 1970
12 more not listed; retrieve them via the Exa API.
3Cited by3 opinions
- Powder Horn Constructors, Inc. v. City of FlorenceSupreme Court of Colorado · 1988
- Powder Horn Constructors, Inc. v. City of FlorenceSupreme Court of Colorado · 1988
- Powder Horn Constructors, Inc. v. City of FlorenceSupreme Court of Colorado · 1988