Legal Opinion

Bangor Hydro-Electric Company v. Federal Power Commission

Court of Appeals for the First Circuit

Decided January 13, 1966No. 6614_1PublishedCited by 1 opinion

1Per curiam

This petition to review an order of the Federal Power Commission refusing reconsideration of an order antedating a license to operate a hydroelectric project on navigable waters is based upon a lack of understanding of our opinion in Central Maine Power Co. v. F.P.C., 1 Cir., 1965, 345 F.2d 875. The facts are essentially similar, and the same result must obtain.

Briefly, in Central Maine Power Co. we held that the Commission was not precluded from antedating a license to the date when a licensee should reasonably have made application or, in the alternative, should have taken note of section…

2Cases cited1 opinion

  1. Central Maine Power Company v. Federal Power CommissionCourt of Appeals for the First Circuit · 1965

3Cited by1 opinion

  1. Niagara Mohawk Power Corporation v. Federal Power CommissionCourt of Appeals for the D.C. Circuit · 1967