Northern Electric Cooperative, Inc. v. Northwestern Public Service Co.
South Dakota Supreme Court
1Opinion of the Court
FOSHEIM, Justice.
This case involves the assignment of approximately a fifty-square-mile territory in the Aberdeen vicinity for electric service pursuant to the provisions of SDCL 49-34A.
The Public Utilities Commission (PUC) assigned most of the area to Northern Electric Cooperative, Inc. (NEC). Northwestern Public Service Company (NWPS) appealed that determination to the circuit court. The trial court reversed and directed the PUC to assign the disputed area in accordance with its opinion. NEC appeals from that decision. The circuit court also assigned a shredder facility, which belongs to…
Also in this document: Concurring in part, dissenting in part.
2Cases cited17 opinions
- Hamilton Gas Light & Coke Co. v. Hamilton CitySupreme Court of the United States · 1892
- Bienville Water Supply Co. v. MobileSupreme Court of the United States · 1902
- Valley State Bank of Canton v. Farmers State BankSouth Dakota Supreme Court · 1973
- Application of Ed Phillips & Sons CompanySouth Dakota Supreme Court · 1972
- State v. DouglasSouth Dakota Supreme Court · 1944
12 more not listed; retrieve them via the Exa API.
3Cited by2 opinions
- Matter of Certain Territorial Elec. Boundaries, Etc.South Dakota Supreme Court · 1979
- West River Electric Ass'n v. Black Hills Power & Light Co.District Court, D. South Dakota · 1989