Legal Opinion

Pennsylvania-Reading Seashore Lines v. Unit Construction Co.

Supreme Court of New Jersey

Decided January 28, 1937PublishedCited by 2 opinions

1Opinion of the Court

The opinion of the court was delivered by

Parker, J.

The suit is by carrier against shipper for freight charges which plaintiff claimed should be paid by the shipper, and which by the terms of the bill of lading are so payable. The trial court allowed, and the Supreme Court approved, the admission of parol evidence to show that the paper-writing which was in duplicate, one part being retained by the carrier and the other part being taken away by the defendant, was not the contract agreed upon by and between the authorized agent of the plaintiff, one Keeper, and the authorized agent of the…

2Cases cited3 opinions

  1. Hill v. Syracuse,Binghamton & New York RailroadNew York Court of Appeals · 1878
  2. Long v. New York Central RailroadNew York Court of Appeals · 1872
  3. Ehnes v. Monroe Loan SocietySupreme Court of New Jersey · 1936

3Cited by2 opinions

  1. Dover Farms, Inc. v. American Air Lines, Inc.New Jersey Superior Court Appellate Division · 1970
  2. Meserve v. TraversoSupreme Court of New Jersey · 1938