Kodiak Industries, Inc. v. Ellis
California Court of Appeal
1Opinion of the Court
Opinion
SPARKS, J.
Under the Mechanics’ Lien Law (Civ. Code, § 3082 et seq.) a claimant who has a direct contract with the owner is required, as a prerequisite to the validity of any claim of lien, to give a preliminary notice to the construction lender or reputed construction lender that a mechanic’s lien may be placed against the property. (Civ. Code, § 3097, subd. (b).) This preliminary notice must be given no later than 20 days after the claimant has first furnished labor, service, equipment or materials to the jobsite. (Civ. Code, § 3097, subd. (c).) If the lien claimant has no actual…
2Cases cited9 opinions
- Connolly Development, Inc. v. Superior CourtCalifornia Supreme Court · 1976
- Walker v. Lytton Savings & Loan Ass'nCalifornia Supreme Court · 1970
- Truestone, Inc. v. Simi West Industrial Park IICalifornia Court of Appeal · 1984
- Schrader Iron Works, Inc. v. LeeCalifornia Court of Appeal · 1972
- Romak Iron Works v. Prudential Insurance of AmericaCalifornia Court of Appeal · 1980
4 more not listed; retrieve them via the Exa API.
3Cited by7 opinions
- Westfour Corp. v. California First BankCalifornia Court of Appeal · 1992
- Brewer Corp. v. Point Center Financial, Inc.California Court of Appeal · 2014
- Shady Tree Farms, LLC v. Omni Financial, LLCCalifornia Court of Appeal · 2012
- Brewer Corp. v. Point Center FinancialCalifornia Court of Appeal · 2014
- Brewer Corp. v. Point Center FinancialCalifornia Court of Appeal · 2014
2 more not listed; retrieve them via the Exa API.