Shell-Con, Inc. v. Architectural Concrete, Inc.
Missouri Court of Appeals
1Opinion of the Court
DOERNER, Commissioner.
This action for damages of $1584.34 for the claimed breach of a written contract originated in the Magistrate Court, where plaintiff was denied relief. Its appeal to the Circuit Court was tried to the court sitting without a jury, and resulted in a judgment for defendant, from which plaintiff appeals. We affirm.
In 1965, defendant and Donco Corporation entered into a written contract whereby Donco agreed to furnish labor and equipment for the unloading and erection of 57 precast concrete canopies, for which the defendant contracted to pay Donco the sum of $7100.00. The…
Also in this document: Per curiam.
2Cases cited10 opinions
- Robbins v. RobbinsSupreme Court of Missouri · 1959
- Dill v. Poindexter Tile CompanyMissouri Court of Appeals · 1970
- Schlanger v. SimonSupreme Court of Missouri · 1960
- Stanziale v. MusickSupreme Court of Missouri · 1963
- Boyd v. BoydMissouri Court of Appeals · 1970
5 more not listed; retrieve them via the Exa API.
3Cited by6 opinions
- McRaven v. F-Stop Photo Labs, Inc.Missouri Court of Appeals · 1983
- Nutz v. ShepherdMissouri Court of Appeals · 1973
- Burrous v. American Airlines, Inc.Missouri Court of Appeals · 1982
- Willsey v. WC Porter Farms CompanyMissouri Court of Appeals · 1975
- Crader v. JamisonMissouri Court of Appeals · 1973
1 more not listed; retrieve them via the Exa API.