Loughlin v. Town of Thompson Planning Board
Appellate Division of the Supreme Court of the State of New York
1Opinion of the CourtCarpinello, J.
In 1991, a 19-lot subdivision was approved by respondent Town of Thompson Planning Board. As a condition of approval, the Board directed that any further subdivision of the lots was subject to its approval. Specifically, in considering any future subdivision application, the Board was to “consider the resubdivision potential of all lots in the subdivision.”
*1335Between 1991 and 2004, eight single-family homes were built on lots 4 through 16 of the subdivision. In January 2004, respondent Cherry Valley Builders, Inc., owner of lot 19, submitted an application to the Board to resubdivide its roughly…
2Cases cited2 opinions
- MLB, LLC v. SchmidtAppellate Division of the Supreme Court of the State of New York · 2008
- Woodland Community Ass'n v. Planning Board of the Town of ShandakenAppellate Division of the Supreme Court of the State of New York · 2008
3Cited by3 opinions
- Dugan v. LigganAppellate Division of the Supreme Court of the State of New York · 2014
- Dugan v. LigganAppellate Division of the Supreme Court of the State of New York · 2014
- MatterofDuganvLigganAppellate Division of the Supreme Court of the State of New York · 2014