Mike Building & Contracting, Inc. v. Just Homes, LLC
New York Supreme Court
1Opinion of the Court
OPINION OF THE COURT
Carolyn E. Demarest, J.
Plaintiff Mike Building & Contracting, Inc. (plaintiff or Mike Building) moves, pursuant to CPLR 3212, for an order granting it partial summary judgment on its first cause of action against Just Homes, LLC (JH) for breach of contract, dismissal of JH’s first counterclaim for breach of contract, and for an award of attorney’s fees and costs. Defendants JH, Albert C. Tew, II, Garry Gutterman, William Berry, Sergio Condi, and James Berry (collectively defendants) move, pursuant to CPLR 3212, for an order granting them partial summary judgment dismissing…
2Cases cited37 opinions
- New York University v. Continental InsuranceNew York Court of Appeals · 1995
- Morris v. New York State Department of Taxation & FinanceNew York Court of Appeals · 1993
- A. S. Rampell, Inc. v. Hyster Co.New York Court of Appeals · 1957
- U.S. Underwriters Insurance v. City Club Hotel, LLCNew York Court of Appeals · 2004
- Aquilino v. United StatesNew York Court of Appeals · 1961
32 more not listed; retrieve them via the Exa API.
3Cited by3 opinions
- National Gear & Piston, Inc. v. Cummins Power Systems, LLCDistrict Court, S.D. New York · 2012
- Pavarini McGovern, LLC v. Waterscape Resort LLC (In re Waterscape Resort LLC)United States Bankruptcy Court, S.D. New York · 2012