1Opinion of the CourtFairchild, J.
Upon the trial in the civil court the evidence established the contract between the city and the appellant, the material portions of which read as follows :
“Paragraph 26. The contractor and sureties hereby agree to indemnify and save harmless the city of Milwaukee from . . . and against any and all claims, liabilities, actions and causes of action, costs, charges, and mechanic’s liens, for labor performed or tools or materials furnished in the construction of the work and any and all costs. ...”
“Paragraph 29. This agreement is, by consent of all parties hereto, made expressly subject to all…
2Cases cited5 opinions
- Yahnke v. LangeWisconsin Supreme Court · 1919
- Wisconsin Electric Sales Co. v. LangdonWisconsin Supreme Court · 1927
- Harper v. McMahonWisconsin Supreme Court · 1918
- Pauly Jail Building & Manufacturing Co. v. CollinsWisconsin Supreme Court · 1909
- Kenese v. Cudahy Bros.Wisconsin Supreme Court · 1918
3Cited by2 opinions
- Crane Co. v. James McHugh Sons, Inc.Court of Appeals for the Tenth Circuit · 1939
- City of Wauwatosa v. VolpanoWisconsin Supreme Court · 1937