Mitchell v. H. B. Zachry Co.
Supreme Court of the United States
1Opinion of the CourtJustice Frankfurter
Once again we are presented with a nice question concerning the scope of the Fair Labor Standards Act, as amended. 63 Stat. 912, 29 U. S. C. § 207. The respondent, a construction contractor, was engaged by the Lower Nueces River Water Supply District (hereafter to be called the District) to construct a dam and impounding facilities on the lower Nueces River in Texas at a cost of about $6,000,000, in order to increase roughly tenfold the District’s then-existing reservoir capacity. The dam is not a multi-purpose project; its sole purpose is to *311create an expanded reservoir for the District. The…
2Cases cited13 opinions
- A. B. Kirschbaum Co. v. WallingSupreme Court of the United States · 1942
- Walling v. Jacksonville Paper Co.Supreme Court of the United States · 1943
- Mitchell v. Lublin, McGaughy & AssociatesSupreme Court of the United States · 1959
- Mitchell v. C. W. Vollmer & Co.Supreme Court of the United States · 1955
- Farmers Reservoir & Irrigation Co. v. McCombSupreme Court of the United States · 1949
8 more not listed; retrieve them via the Exa API.
3Cited by127 opinions
- Spiegel, Inc. v. Federal Trade CommissionCourt of Appeals for the Seventh Circuit · 1976
- James P. Mitchell, Secretary of Labor, United States Department of Labor v. Mitchell Truck Line, Inc.Court of Appeals for the Fifth Circuit · 1961
- Sobrinio v. Medical Center Visitor's Lodge, Inc.Court of Appeals for the Fifth Circuit · 2007
- W. Willard Wirtz, Secretary of Labor, U. S. Department of Labor v. B. B. Saxon Company, Inc.Court of Appeals for the Fifth Circuit · 1966
- Mays v. Midnite Dreams, Inc.Nebraska Supreme Court · 2018
122 more not listed; retrieve them via the Exa API.